Plenty of head contractors will not take a payment claim by email. They require it to be lodged in their own software: Payapps, Oracle Aconex, Procore, or something built in-house. You do not get a choice about it, and doing what your contract tells you to do is not a problem to be solved.
The problem is what it leaves you with. A subcontractor working for four head contractors has claims sitting in four portals, none of which knows about the others. Nothing tells you what you have claimed across the job, what retention is held, or which head contractor's response is due first, and the response deadlines are running the whole time.
You can record those claims here, so that one place knows. This page explains exactly what that does and what it does not do.
What recording one means
The platform calls a claim you lodged elsewhere an externally served claim, and labels it Externally served wherever it appears: in your claims lists, on your dashboard, and beside the deadline in your Needs attention feed. The claims register you can export carries the same fact in an Origin column, where it reads EXTERNAL: that sheet writes its status columns as plain values so you can filter and pivot on them.
Recording one is bookkeeping, not claiming. The claim already exists: you lodged it, and it had legal effect the moment it was served, whatever this platform does afterwards. What recording it does is bring it into your ledger and start counting its deadlines.
There are two ways to do it, and they end in the same place:
Type it in. You enter the claim line by line against your contract's own items, with the amount claimed and the retention withheld as the portal's document states them, plus the claim's reference from that document and the date it was served.
Read it off the document. If you have the portal's claim as a file, the platform can read the figures out of it and show you what it found, set against your contract's own items, so you are checking figures rather than working from a blank page. Every figure is yours to correct, and any line that does not match something on your contract is called out for you to place or to fix the contract for. The reading waits while you do, and nothing is re-read when you come back to it. When you are happy with it, one button records the lot: the claims land the same way as if you had typed them in, in period order. Nothing is recorded from that read until you press it. Reading a document costs nothing; see what it costs below.
Either way the claim lands on your contract's next unclaimed period, in sequence, exactly as a claim you made here would.
It is not "history"
The platform also lets you load historic claims at setup: the claims that came and went before you started using it, so your contract's opening position is right. Those two things sound similar and are not.
The difference is whether the claim is finished, not how old it is.
- A claim that was certified and paid two years ago is history. It records a closed outcome. The platform carries its figures in the ledger and nothing else: no deadline, no chasing, and no fee.
- A claim still waiting for the head contractor's answer is an externally served claim, even if you lodged it months before you ever signed up here. It is live. Its statutory clock is running, and tracking it is the whole point.
"Old claim, therefore history" is the natural assumption and it is the wrong one. If nobody has certified it yet, it belongs in the second group.
One thing to do in the right order. Recording a claim on a contract (a portal claim included) closes that contract's history, and the earlier periods can no longer be filled in afterwards. So where a job was already running before you set it up here, load its finished claims first and record the live portal one after. The record form warns you when a contract still has earlier periods outstanding, but this is much easier to get right at the outset than to unpick later.
What the platform does with it, and what it does not
It generates nothing and serves nothing. The head contractor's portal produced the claim document. There is no claim PDF of ours for that claim and there never will be one. The claim page says so in as many words rather than leaving you to notice an empty space. Your own copy of the portal's document can be attached to the claim as evidence, alongside anything else you keep with it.
It records how the claim was served. The service method is lodgment, and the date of service is the date you tell it. The platform cannot see the portal's clock, the same way it cannot see whether a letter arrived, so it asks you and records your answer.
Every deadline it tracks runs from that date. The claim goes into your Needs attention feed, the head contractor's response deadline is counted in your contract's jurisdiction, the reminders go out, and the claim appears in the register alongside everything else. Nothing in that arithmetic depends on where the claim was lodged.
It does not decide whether your lodgment was valid service under the Act. Whether lodging a claim in a head contractor's system counts as service turns on your contract's service clause and on the legislation, and that is not the platform's call to make. It counts from the date it is told, and the pages that name your next statutory step say so plainly rather than implying the claim was well served. That is a limit on what the platform asserts, not a suggestion that anything is wrong with your claim.
The clock, and what it is counted from
The head contractor's response deadline is counted from the recorded date of service on the claim: the date shown on the claim page, which is what every deadline on it derives from.
That is usually the day you lodged it, and it is worth knowing when it is not. Some acts deem a claim served before its window opens to have been served on the first day it could have been, so that serving early never shortens the other side's time to respond. Where that applies, the platform records the later date, because that is the date the legislation counts from, so the recorded date of service can sit a little after the day you actually lodged. The summary below says which jurisdictions do this, with the section it comes from.
Recording the claim late does not move anything. The deadline was set when the claim was served; recording it a week afterwards produces the same dates, with less of the window left to watch.
Here is what each jurisdiction allows, and the provision each figure comes from:
Western Australia
Building and Construction Industry (Security of Payment) Act 2021 (WA)
- Payment schedule due
- 15 business days s 25(1)(b)
- Payment due
- 25 business days s 20(1)(b)
- Claim can be served from
- On or after the last day of the month the claim covers. s 23(2)
- And no later than
- Within 6 months after the work the claim relates to was last carried out. s 23(4)(b)
- Releasing retention
- A claim for the final payment runs to the later of 28 days after the defects liability period ends and 6 months after all the work was completed. s 23(5)(b) to (d)
- If no schedule arrives
- The respondent becomes liable to pay the full claimed amount on the due date. You may then recover it as a debt in court or apply for adjudication, but not both. ss 26, 27(2)
- A further chance to schedule
- 5 business days s 28(2) Only where the respondent gave no payment schedule at all. The claimant must give written notice of their intention to apply for adjudication within 20 business days after the due date for payment, and the window runs from the respondent’s receipt of that notice. It does not move the due date for the progress payment (s 28(3)).The platform states this window. It does not count it, because the notice that starts it happens off the platform.
New South Wales
Building and Construction Industry Security of Payment Act 1999 (NSW)
- Payment schedule due
- 10 business days s 14(4)(b)(ii)
- Payment due
- 20 business days s 11(1B)(a)
- Claim can be served from
- On and from the last day of the named month the claim covers, or the earlier date your contract sets. s 13(1A) to (1B)
- And no later than
- Within 12 months after the work the claim relates to was last carried out. s 13(4)(b)
- If no schedule arrives
- The respondent becomes liable to pay the full claimed amount on the due date, and you may recover it as a debt. ss 14(4), 15
- A further chance to schedule
- 5 business days s 17(2)(b) Only where the respondent gave no payment schedule and did not pay. The claimant must serve written notice of their intention to apply for adjudication within the 20 business days immediately following the due date for payment, and the window runs from the respondent’s receipt of that notice.The platform states this window. It does not count it, because the notice that starts it happens off the platform.
Victoria
Building and Construction Industry Security of Payment Act 2002 (Vic)
- Payment schedule due
- 10 business days s 15(4)(b)(ii)
- Payment due
- 20 business days s 12(1B)
- Claim can be served from
- On and from the last day of the month the claim covers. Two Victorian quirks: a claim served early is treated as served on the first day it could have been, so serving early never shortens the response clock; and work carried out between 22 and 31 December can only be claimed on and from 31 January. ss 14A(2)(b), 14A(5)(c)
- And no later than
- Up to the day before the date 6 months after practical completion. s 14C(b)
- Releasing retention
- Retention is released by a separate instrument: a performance security claim. It may be served from whichever comes first of 20 business days after the defects liability period ends and the day your contract nominates, and it closes on the last day of the month following the month that defects liability period ends. ss 17B(1), 17C(b)
- If no schedule arrives
- The respondent becomes liable to pay the full claimed amount on the due date, and you may recover it as a debt. ss 15(4), 16
- A further chance to schedule
- 5 business days ss 18(2), 18(2A) Only where the respondent served no payment schedule and paid or released nothing by the due date. Victoria gives the claimant a shorter run at it than the other states: notice of their intention to apply for adjudication must be served within 10 business days after the due date, and the window runs from the respondent’s receipt of that notice. The same step applies to a performance security claim (s 18A(2)).The platform states this window. It does not count it, because the notice that starts it happens off the platform.
Queensland
Building Industry Fairness (Security of Payment) Act 2017 (Qld)
- Payment schedule due
- 15 business days s 76(1)(b)
- Payment due
- 10 business days s 73(1)(b)
- Claim can be served from
- On or after the reference date: the day your contract nominates, defaulting to the last day of each month. s 67
- And no later than
- Within 6 months after the work the claim relates to was last carried out. s 75(2)(b)
- Releasing retention
- A claim for the final payment may be given up to 28 days after the last defects liability period ends. s 75(3)(b)
- If no schedule arrives
- The respondent becomes liable to pay the full claimed amount and you may recover it as a debt. Queensland goes further than the other states: failing to respond is itself an offence, carrying up to 100 penalty units. ss 76, 77, 78
Australian Capital Territory
Building and Construction Industry (Security of Payment) Act 2009 (ACT)
- Payment schedule due
- 10 business days s 16(4)(b)(ii)
- Payment due
- 15 business days s 13(1)
- Claim can be served from
- On or after the last day of the calendar month the claim covers. s 15
- And no later than
- Within 12 months after the work the claim relates to was last carried out. s 15(5)(b)
- If no schedule arrives
- The respondent becomes liable to pay the full claimed amount on the due date, and you may recover it as a debt. ss 16(4), 17
- A further chance to schedule
- 5 business days s 19(2)(b) Only where the respondent gave no payment schedule and did not pay the claimed amount by the due date. The claimant must notify the respondent of their intention to apply for adjudication within the 20 business days immediately following the due date, and the window runs from the respondent’s receipt of that notice.The platform states this window. It does not count it, because the notice that starts it happens off the platform.
South Australia
Building and Construction Industry Security of Payment Act 2009 (SA)
- Payment schedule due
- 15 business days s 14(4)(b)(ii)
- Payment due
- 15 business days s 11(1)(b)
- Claim can be served from
- On and from the reference date: the day your contract nominates, defaulting to the last day of each named month. ss 4, 8
- And no later than
- Within 6 months after the work the claim relates to was last carried out. s 13(4)(b)
- If no schedule arrives
- The respondent becomes liable to pay the full claimed amount on the due date, and you may recover it as a debt. One exception is unique to South Australia: on a Crown contract worth more than $4 million excluding GST, the no-schedule consequence and adjudication are unavailable against the Crown party, though your own subcontracts underneath are unaffected. ss 14(4), 15; Regulations r 7
- A further chance to schedule
- 5 business days s 17(2)(b) Only where the respondent gave no payment schedule and did not pay the claimed amount by the due date. The claimant must notify the respondent of their intention to apply for adjudication within the 20 business days immediately following the due date, and the window runs from the respondent’s receipt of that notice.The platform states this window. It does not count it, because the notice that starts it happens off the platform.
Tasmania
Building and Construction Industry Security of Payment Act 2009 (Tas)
- Payment schedule due
- 10 business days s 19(3)(b)
- Payment due
- 10 business days s 15(2)
- Claim can be served from
- On or after the reference date: the day your contract nominates, defaulting to the last day of each month in which you carried out work. s 4
- And no later than
- Within 12 months after the work the claim relates to was last carried out. s 17(6)(b)
- If no schedule arrives
- The respondent becomes liable to pay the full claimed amount on the due date. Tasmania collects the recourse in one place: debt recovery, adjudication and the right to serve a suspension notice all sit within the same section. s 19(2), (4) to (8)
- A further chance to schedule
- 5 business days s 21(4) Only where the respondent gave no payment schedule and did not pay. The claimant must notify the respondent within 20 business days after the due date both that they intend to apply for adjudication and that a payment schedule may still be provided. Tasmania alone counts the window from when that notice is given rather than from when it is received.The platform states this window. It does not count it, because the notice that starts it happens off the platform.
New Zealand
Construction Contracts Act 2002 (NZ)
- Payment schedule due
- 20 working days s 22(b)(ii)
- Payment due
- 20 working days s 18
- Claim can be served from
- At the end of the relevant period: monthly by default, ending on the last day of the month. ss 17(2), 20(1)
- And no later than
- No statutory longstop: the Act imposes no cap on how long after the work a claim may be served.
- If no schedule arrives
- The payer becomes liable to pay the full claimed amount, recoverable as a debt, and you gain the right to suspend work on notice. ss 22, 23
For what the deadline means once it passes, see when no schedule arrives. The limit above applies there too: the platform tells you the window has closed and what the Act provides, and does not determine whether your lodgment effected service.
Why the retention figure may not match
The retention on an externally served claim is what the portal withheld, transcribed from its document. That figure is what actually came off your claim, so that is what the ledger carries. The platform does not overwrite it.
It does check it. Your contract records how retention should be calculated, so the platform works out what that method would have withheld on the same lines and tells you when the two disagree, naming both figures, so you can hold the warning up against the portal's own document and see which one is wrong. It stays a warning, and the transcribed figure is still what gets recorded.
Two things usually explain a gap. The document was read wrong, which is the easier one to fix. Or the head contractor withheld on a basis your contract does not provide for, which is worth catching in the month it happens rather than discovering years in, the subject of when the numbers do not match.
When their answer comes back
Record the payment schedule against the claim exactly as you would for any other claim. Nothing about the recording step differs because the claim was lodged elsewhere. See recording a schedule you have received.
From that point the certified figures supersede the claimed ones in your running totals, the retention position updates, and the claim stops appearing in your Needs attention feed.
Fixing one you got wrong
An externally served claim stays editable until a payment schedule is recorded against it, and freezes afterwards. That is more forgiving than a claim served through the platform, which is immutable from the moment it goes out, and you are transcribing someone else's document here, so the platform assumes you may need a second pass at it. Editing is free, however many times you do it.
Two limits worth knowing. Once a claim has been recorded on your billing history it can no longer be removed: that entry is what stops one claim being charged twice, and it exists whether the claim was charged in full, included at the monthly cap, or waived at nil. Correct it by editing instead. And a claim recorded against the wrong contract cannot be moved to the right one; that one needs support, and the Help control in the app header has the link.
What it costs
Recording a claim you lodged elsewhere is charged like any other claim on the platform. What the fee pays for is the tracking (the deadlines, the reminders, the ledger, the register) as much as the document, and on these claims you get the tracking without the document, because the portal produced that.
Where one reading holds several claims, each is charged as its own claim, and you are asked once: the confirmation names how many claims are about to be recorded and what the total comes to before you press it.
Some things that are not charged: reading a portal document to fill the form, editing a claim after you record it, and recording the payment schedule when it comes back. And loading a contract's pre-onboarding history at setup is free: those claims are finished, so there is nothing to track, which is both why they are free and why they carry no deadlines.
The current fee, the monthly cap and the free trial are on the pricing page, and the Access Terms set out exactly which acts are chargeable.
General information, not legal advice
This page describes how the platform records and tracks a claim lodged in someone else's system. Whether a particular lodgment effected service under your contract and the relevant Act is a question about your contract and your situation, and the platform is not a law firm. Where something is at stake, get advice.