These are the statutory timings under the Building and Construction Industry (Security of Payment) Act 2021 (WA). They are what the platform counts to on a Western Australia contract, with the exceptions noted below.
If your contract heads the document a progress claim, these are your deadlines too: progress claim and payment claim are two names for the same document, and the Act uses the second.
- Payment schedule due
- 15 business days s 25(1)(b)
- Payment due
- Head contract: 20 business days after service s 20(1)(a)Subcontract: 25 business days after service s 20(1)(b)
- Payment schedule, if the contract sets a time
- Where the contract sets its own time for the payment schedule, the deadline is the earlier of that and the period above. s 25(1)(a)
- Claim can be served from
- On or after the last day of the month the claim covers. s 23(2)
- And no later than
- Within 6 months after the work the claim relates to was last carried out. s 23(4)(b)
- Releasing retention
- A claim for the final payment runs to the later of 28 days after the defects liability period ends and 6 months after all the work was completed. s 23(5)(b) to (d)
- If no schedule arrives
- The respondent becomes liable to pay the full claimed amount on the due date. You may then recover it as a debt in court or apply for adjudication, but not both. ss 26, 27(2)
- A further chance to schedule
- 5 business days s 28(2) Only where the respondent gave no payment schedule at all. The claimant must give written notice of their intention to apply for adjudication within 20 business days after the due date for payment, and the window runs from the respondent’s receipt of that notice. It does not move the due date for the progress payment (s 28(3)).The platform states this window. It does not count it, because the notice that starts it happens off the platform.
- If the scheduled amount is not paid
- If the respondent does not pay the scheduled amount in full by the due date, the claimant may recover the unpaid portion as a debt in court or apply for adjudication, but not both. In the debt proceedings the respondent cannot cross-claim or raise a defence arising under the contract. The claimant may also suspend work on notice. ss 27(2), 27(3)(b), 62Suspend work: 2 business days s 62(4) Counted from the claimant giving written notice of their intention to suspend work, stating that it is given under the Act.Apply for adjudication: 20 business days s 28(4) Counted from when the claimant first becomes entitled to apply. For an unpaid scheduled amount that is the due date for payment, unless the schedule was already for less than the claimed amount, in which case the entitlement arose when the claimant received it (s 28(1)).The platform states these periods. It does not count them.
How to read a citation
"s 14(4)(b)(ii)" is a section, subsection and paragraph of the Act named above. Every deadline the platform counts comes from the consolidated Act its own deadline engine is built from, and is checked against that engine automatically. If the two ever disagreed, the platform would fail to build rather than publish a number it does not itself use. Two kinds of figure are the exception, and each is marked where it appears. The first is the further chance to give a payment schedule. That window opens only if the claimant serves a notice of intention to apply for adjudication, which happens off the platform, so the Act's rule is stated here without a clock behind it. The second is the periods that follow a scheduled amount going unpaid: the wait after a notice of intention to suspend work, and the time to apply for adjudication. The platform does not track either step, so those are stated without a clock behind them too.
General information, not legal advice
These are the statutory defaults. Your contract can vary some of them (always in the direction of a shorter schedule window, sometimes in the direction of a longer claiming period) and none of this is advice about your situation. Where a deadline matters, check the Act and take advice.
What these terms mean
The deadlines above are counted in business days as the Act itself defines them: weekends and public holidays excluded, and in several jurisdictions a Christmas shutdown as well. If the vocabulary is new, start here:
- What a payment claim is: The document, what makes it valid, and why it is not an invoice.
- Progress claims and payment claims: Two names for the same document, and the one word that has to be on it.
- Payment schedules: The head contractor's reply, its deadline, and what happens when it never arrives.
- Claims lodged in a head contractor's portal: Claiming through Payapps or Aconex: what the platform records, and what it does not do.
- Retention: What is held back from each claim, and when you get it back.
- Reference dates and claim periods: Which dates a claim covers, and the earliest day you can serve it.
- Glossary of claim and contract terms: What your contract calls it, what the Act calls it, and what it means.